SMART Zambia Phase 2 Project

Sub Project Name Progress
NBN-Backbone ●First workshop carried out with SZI and Solution is under discussion
ZNDC ●Kick off meeting done
●Data center L1 design done
Capacity Building ●Training center building design is in progress, 80% finished. Excepted to be finished early April.
●LMS (e-learning system)requirements survey is started this week with ICT College project team.
●Low level design is done (except LMS) , under review with ICT college project team.
ICCC ●Solution is under discussion
Campus Network ●159 sites survey completed
●Pilot site implementation done
●17 sites is under Implementation
E-Education ●Optimized and consolidated the solution by adding the peripheral equipment and enhanced the training.
E-Customs ●Solution presented to ZRA and waiting for ZRA official URs. ( user requirements)
●Survey done for ZRA proposed data center site, survey report is provided to ZRA